Large energy users are building their own power plants on or near their sites to avoid years of waiting for grid connections. SpaceX plans a gas plant at Starbase, Texas, and Dow has a federal permit for small reactors at its Texas chemical plant. Self-supply shortens the path to power, but projects still need local approval, fuel and air permits, and land suited to generation.
Key Takeaways
SpaceX plans a roughly $24 billion gas-fired power plant and supercomputing facility at Starbase, Texas, that it would build, own and operate.
Owning the plant could let SpaceX avoid a years-long wait to connect to the Texas grid, according to Reuters.
The Nuclear Regulatory Commission (NRC) issued a construction permit on November 9 for four X-energy reactors to supply steam and power at Dow’s Seadrift chemical plant.
PJM’s market monitor recommends a faster connection path for data centers that bring their own generation.
Self-supply moves the approval fight from the grid queue to local governments, fuel supply and permits.
SpaceX plans to invest an initial estimated $24 billion for a gas-fired power plant and supercomputing facility on a 444-acre tract within Starbase, Texas, east of Brownsville, according to a public hearing notice reported by Reuters and Bloomberg. SpaceX would build, own and operate both. The notice did not disclose the plant’s generating capacity or the size of the computing operation.
The reason is time. Owning a power plant could let SpaceX avoid a years-long wait to connect to the main Texas grid, Reuters reported. A SpaceX affiliate has also filed plans for an 8-mile natural gas pipeline at Starbase, due in service by January 2027, to supply a plant that converts gas into liquid methane for rockets. Bloomberg tied the project to a broader SpaceX effort to secure its own gas supply. The Starbase City Commission will consider a property tax abatement and development agreement on December 9.
SpaceX is also behind a proposed 750-acre campus in Cochise County, Arizona, that would reach 6,000 MW at full buildout and include battery storage, KJZZ reported. It was not immediately clear what the Arizona project would cost.
Steam and Power From Reactors at a Chemical Plant
Dow is taking the same idea in another direction. On November 9, the NRC issued a construction permit to Long Mott Energy, a Dow subsidiary, for four X-energy Xe-100 high-temperature gas-cooled reactors at Dow’s Seadrift Operations in Calhoun County, Texas. The plant would mainly supply high-temperature steam for industrial use, with excess electricity sent to the grid. The American Nuclear Society describes the project as 320 MW of electricity.
It is the first construction permit for a reactor of this type in nearly 60 years, and NRC Chairman Ho K. Nieh said the agency “delivered on the 18-month schedule.” The permit allows construction only; an operating license is still required, and Dow expects a preliminary investment decision in 2027, with commercial operation targeted for the early 2030s.
For industrial owners, the Dow project matters because it replaces both electricity and process heat. Steam is the larger energy need at many plants, and a source that supplies both on the same site can replace aging boilers as well as grid power.
Why Self-Supply Is Spreading
Grid capacity is the constraint. PJM’s independent market monitor recommends that large data centers connect only when capacity exists to serve them, while creating an expedited path for those that bring their own generation. In New England, the regional grid operator has proposed that large loads seeking firm service match their demand with new capacity, and that flexible loads be able to run onsite generation when prices spike.
Developers are testing the model at large scale. In Alaska, a draft impact analysis prepared for the state Department of Natural Resources describes the STAK Energy Campus near Prudhoe Bay as a gas-powered computing facility with 1 GW to 3 GW of onsite generation on about 715 acres of state land. Each project places generation where fuel and land are available and treats the grid connection as optional or secondary.
The Firsts in Dow’s Permit
The Dow permit carries several regulatory firsts that matter beyond one plant. It is the NRC’s first approval of a multimodule advanced reactor design, its first approval of a pebble-bed core and its first approval of online refueling, and the first high-temperature gas-cooled reactor reviewed under the agency’s modernized licensing framework. The NRC issued its environmental assessment in May and finished its safety evaluation in October, a month ahead of schedule. It is the third advanced reactor construction permit the agency has issued this year.
Each Xe-100 unit is rated at 80 MW of electricity and 200 MW of thermal output, according to the American Nuclear Society. That mix suits industrial users whose largest need is heat. A faster, more predictable licensing path makes onsite reactors a planning option for large industrial campuses in the 2030s, though not a near-term one.
Fuel, Land and Transmission Still Matter
Gas-fired self-supply depends on fuel prices and pipelines. The U.S. Energy Information Administration (EIA) forecasts Henry Hub natural gas at $3.37 per million British thermal units for 2026 and $2.88 for 2027, with a winter average of $2.87, lower than it expected a month earlier. Low gas prices support onsite generation economics, and they can change.
Land assembly follows the power plan. In Cochise County, Tombstone Resources will buy another 348 acres from Southline Transmission to complete the SpaceX-linked site, KJZZ reported. The same report noted that Mississippi environmental regulators found SpaceX began construction on a data center there without necessary permits, a reminder that speed to power can collide with state permitting.
The Approvals Move Local
Self-supply avoids one queue and joins others. SpaceX’s Starbase project needs a local tax abatement. Gas plants need air permits and fuel supply; reactors need federal licensing at every stage. And the local climate for large projects has hardened. Voters rejected data centers in 40 of 41 local ballot measures on November 3, according to the Reuters report on SpaceX. Lee County, Georgia, has extended its data center moratorium to June 2027, and Vance County, North Carolina, extended its pause as drought lowered its water supply.
Texas politics may shift as well. Bloomberg noted that the state’s incoming governor campaigned partly on curbing data center construction. A project that supplies its own power still needs a community willing to host it.
What It Means for Owners and Developers
Implication: Land suited to generation gains value. Sites with gas pipeline access, room for a power plant and industrial zoning become more marketable to large users, especially where grid queues are long.
Implication: Industrial heat is in play. Projects like Dow’s show onsite generation can replace steam as well as electricity, which matters for chemical, food and manufacturing campuses.
Opportunity: Neighboring tenants and microgrids. A campus that generates its own power may sell surplus to the grid or to nearby users, depending on state rules, creating a distributed energy cell around the site.
Risk: Fuel and permit exposure. A gas-fired campus carries fuel price and supply risk and air permit conditions that grid-connected buildings avoid.
Risk: Local opposition. Tax abatements, zoning and water use remain local decisions, and the November ballot results show how quickly communities can act.
Frequently Asked Questions
Why are companies building their own power plants?
To avoid waiting years for grid connections. Reuters reported that owning its plant could let SpaceX avoid a years-long wait to connect to the Texas grid.
What did the NRC approve for Dow?
A construction permit for four X-energy Xe-100 reactors at Dow’s Seadrift site in Texas to supply steam and power. An operating license is still required.
Does self-supplied power avoid local approval?
No. Projects still need local tax, zoning and permit decisions, plus air permits and fuel supply for gas plants.
What does this mean for industrial land?
Sites with fuel access, room for generation and industrial zoning become more valuable to large energy users.
Sources
American Nuclear Society. “NRC Issues Construction Permit for Dow/X-energy Long Mott Project.” Nov. 10, 2026. https://www.ans.org/news/article-8573/nrc-issues-construction-permit-for-dowxenergy-long-mott-project/
Bloomberg via Insurance Journal (Dana Hull and Julian Hast). “SpaceX Plans $24 Billion Data Center and Gas Plant in Texas.” Nov. 10, 2026. https://www.insurancejournal.com/news/southcentral/2026/11/10/892283.htm
ISO New England (ISO Newswire). “ISO-NE Files Proposal With FERC to Address Large Loads.” Nov. 13, 2026. https://isonewswire.com/2026/11/13/iso-ne-files-proposal-with-ferc-to-address-large-loads/
KJZZ (Greg Hahne). “SpaceX Is Behind Proposed Data Center in Cochise County.” Nov. 10, 2026. https://www.kjzz.org/fronteras-desk/2026-11-10/spacex-is-behind-proposed-data-center-in-cochise-county
Monitoring Analytics (Independent Market Monitor for PJM). “2026 Quarterly State of the Market Report for PJM: January Through September, Section 1.” Nov. 12, 2026. https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2026/2026q3-som-pjm-sec1.pdf
Reuters via WHTC (Akash Sriram). “SpaceX Plans $24 Billion Gas Power Plant, Data Center Project in Texas.” Nov. 9, 2026. https://whtc.com/2026/11/09/spacex-plans-24-billion-gas-power-plant-data-center-project-in-texas/
STAK Energy Corporation for Alaska Department of Natural Resources. “STAK Energy Campus: Cumulative Impact Analysis (draft).” April 2026. https://aws.state.ak.us/OnlinePublicNotices/Notices/Attachment.aspx?id=161961
U.S. Energy Information Administration. “Short-Term Energy Outlook, November 2026.” Nov. 10, 2026. https://www.eia.gov/outlooks/steo/archives/nov26.pdf
U.S. Nuclear Regulatory Commission. “NRC Issues First Construction Permit in Nearly 60 Years for High-Temperature Gas-Cooled Reactor (News Release 26-083).” Nov. 9, 2026. https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2026/26-083.pdf
WALB. “Lee County Board of Commissioners Extends Moratorium on Data Centers to End of Next June.” Nov. 11, 2026. https://www.walb.com/2026/11/11/lee-county-commissioners-extend-moratorium-data-centers-into-next-summer/
WIZS. “Vance Commissioners Vote to Extend Data Center Moratorium.” Nov. 15, 2026. https://wizs.com/vance-commissioners-vote-to-extend-data-center-moratorium/