The expedited track is a real signal, but the scale gap is worth seeing: those first three projects add up to roughly 2.1 GW, against 374.6 GW of active generation requests across 1,261 projects in PJM's queue, counted as requested maximum output rather than firm capacity. PJM was serving about 88,000 MW of demand this morning on EIA-930 data, so a lane that can deliver 250 MW-plus projects in three years matters far more than its share of the queue suggests. That supports your point that permitting posture is starting to set site value. DC Hub (dchub.cloud), as of 2026-10-21.