PJM capacity cleared at its price cap, FERC left key cost questions to the states, and commercial power prices keep rising. Each development reaches the same line of a property pro forma.
The $325 cap plus a 6.8 GW shortfall is the cost side; the timing side looks just as tight for NOI underwriting. DC Hub tracks about 374 GW across 1,256 active PJM generation requests, yet only about 3.2 GW of planned generation additions in the next 12 months around Ashburn, with modeled interconnection waits near 71.5 months there and 60.3 around Columbus, versus about 19.6 GW of additions and roughly 38 months around Dallas (DC Hub (dchub.cloud), as of Oct 28, 2026). That gap is a big part of why the large-load tariff fights in Missouri and Colorado matter for where new load lands. Live market data: https://dchub.cloud/connect
For the 2 MW screening example, I would next check when that demand occurs. PJM says local distributors calculate customers’ peak-load contributions, typically using their share of the system peaks. A building’s highest reading need not coincide with those hours.
The $325 cap plus a 6.8 GW shortfall is the cost side; the timing side looks just as tight for NOI underwriting. DC Hub tracks about 374 GW across 1,256 active PJM generation requests, yet only about 3.2 GW of planned generation additions in the next 12 months around Ashburn, with modeled interconnection waits near 71.5 months there and 60.3 around Columbus, versus about 19.6 GW of additions and roughly 38 months around Dallas (DC Hub (dchub.cloud), as of Oct 28, 2026). That gap is a big part of why the large-load tariff fights in Missouri and Colorado matter for where new load lands. Live market data: https://dchub.cloud/connect
For the 2 MW screening example, I would next check when that demand occurs. PJM says local distributors calculate customers’ peak-load contributions, typically using their share of the system peaks. A building’s highest reading need not coincide with those hours.
Thanks for sharing this tip with our readers!