The United States could run short of the transformers and switchgear that connect buildings to the grid as early as 2027, according to a Johns Hopkins study, and lead times already exceed two years. For property owners, the constraint shows up as delayed service upgrades, charger installations and tenant move-ins. Ordering early, standardizing specifications and keeping existing equipment healthy reduce the risk.
Key Takeaways
Johns Hopkins University researchers project U.S. shortages of transformers, converters and other grid equipment as early as 2027, with acute shortages by 2030.
Under high demand growth, the shortfall reaches almost 15% for transformers and 30% for other critical equipment; a trade disruption widens the gaps to about 25% and 36%.
Copper runs short first, and data centers could drive up to two-thirds of the equipment gap.
Transformer lead times have quadrupled in four years to more than two years, Fortune reported.
Owners planning service upgrades, EV charging or onsite generation should order long-lead equipment at design development and build delays into leases and loans.
Copper Runs Out First
15% is the shortfall in power transformers Johns Hopkins University researchers project under high electricity demand growth, alongside a 30% shortfall in other grid-supporting equipment such as converters, in a study published in Cell Reports Sustainability and announced November 17. Shortages could begin as early as next year and turn acute by 2030.
Materials drive the gap. Copper runs short first, affecting equipment for data centers, wind power converters and EV charging infrastructure, and steel and nickel become nearly impossible to source by 2030, the researchers found. Data centers could account for up to two-thirds of the expected shortages. If trade disruptions cut materials from unstable partners by up to 70%, the transformer gap widens to about 25% and the gap for other equipment to about 36%.
Modest growth does not solve the problem. In the baseline case, the country would likely have enough transformers by 2030 but still fall about 16% short on other grid equipment. “By 2030 we’re likely to have transformer shortages even without the most aggressive power demand growth,” said Yury Dvorkin, a Johns Hopkins associate professor and the study’s lead researcher.
Lead Times Already Stretch Past Two Years
The queue is already long. Transformers are usually custom-built, and lead times have quadrupled in four years, from about six months to more than two years, Fortune reported. Reuters reported in July that lead times for generator step-up transformers passed 160 weeks in early 2026 and high-voltage circuit breakers reached 125 weeks, with transformer prices expected to rise 4% to 10% over the next year.
Utilities are adapting. Roseville Electric Utility in California once bought equipment about a year ahead and now buys for substation projects it expects five years out, Reuters reported. Scarce supply will go to the highest bidder. “Will it be a mom-and-pop utility or a big data center corporation?” Dvorkin asked in Fortune. JPMorganChase estimates the grid will need about $1 trillion in investment through 2035.
Winter Shows Where New Equipment Matters
This winter’s reliability outlook shows how much the grid leans on new hardware. The North American Electric Reliability Corporation (NERC) reports that on-peak capacity grew 26.2 GW from last winter, led by batteries and gas-fired generation, while 21 of 23 assessment areas raised their demand forecasts. Federal Energy Regulatory Commission (FERC) staff count batteries as 27%, or 21.6 GW, of new winter capacity additions.
Every one of those projects needs transformers, inverters and switchgear to connect. So do the chargers, heat pumps and service upgrades that electrify buildings. Owners compete for the same factory slots as utilities and hyperscalers.
How the Shortage Reaches a Building
Two kinds of equipment stand between a building and more power. The utility typically owns the service transformer and the upstream lines, so a new service or upgrade waits on the utility’s own procurement queue. The owner buys the switchgear, panels and distribution equipment on the building side, along with charger power cabinets and onsite generation interconnection gear.
Either side can set the schedule. A tenant fit-out that needs a larger service, a fleet depot that needs megawatts for chargers or a retrofit that replaces gas boilers with heat pumps can sit finished and unpowered while equipment arrives. Copper shortages compound the problem because the same metal goes into transformers, cable and EV charging hardware, the Johns Hopkins researchers found. Lease commencement dates, rent abatement clauses and construction loan milestones built on six-month equipment assumptions now carry real exposure.
Supply Is Growing, Slowly
Manufacturers are adding capacity, and some of it serves building projects directly. Alpitronic will begin assembling 400 kW and 1 MW fast chargers in Fort Mill, South Carolina, in February 2027. Dell’Oro Group projects that solid-state transformers, which replace a conventional transformer, switchgear and uninterruptible power supply with one software-controlled unit, will approach $6 billion of the data center power market by 2030.
The Johns Hopkins team recommends steps that stretch existing supply: low-cost sensors that monitor transformer loads in real time, recycling materials from retired units and standardized designs so one transformer can replace another. Each applies at the building level as well as the utility level.
A Six Step Equipment Plan for Owners
Inventory what you own. Record the age, rating and condition of transformers, switchgear and panels across the portfolio, and flag units near end of life or at capacity.
Ask the utility early. Request service capacity and upgrade requirements at site selection or schematic design, before tenants sign, so utility-owned equipment enters the queue in time.
Order long-lead gear at design development. Release purchase orders for transformers, switchgear and charger power cabinets as soon as ratings are fixed, and consider owner-furnished equipment to secure factory slots.
Standardize specifications. Common voltages and ratings across properties make spares interchangeable and widen the pool of available units.
Extend the life of what works. Load monitoring, maintenance and refurbishment defer replacements and reduce emergency exposure.
Write delay into contracts. Lease delivery dates, construction loan milestones and financing draws should allow for equipment delays measured in quarters.
What It Means for Owners and Developers
Implication: Power readiness becomes a leasing advantage. Buildings with spare electrical capacity and modern switchgear can deliver space and chargers sooner.
Risk: Electrification schedules slip. Heat pump conversions, fleet charging and onsite generation all depend on the same constrained equipment.
Opportunity: Spares hold value. Standardized spare transformers and switchgear reduce downtime risk and support insurance and lender reviews.
Frequently Asked Questions
When could transformer shortages begin?
Johns Hopkins researchers project shortages as early as 2027, with acute shortages by 2030.
How large could the shortfall be?
Under high demand growth, almost 15% for transformers and 30% for other grid equipment; a trade disruption widens those gaps to about 25% and 36%.
How long are transformer lead times?
Fortune reports lead times of more than two years, and Reuters reported generator step-up transformers above 160 weeks in early 2026.
What can property owners do?
Inventory equipment, request utility capacity early, order long-lead gear at design development, standardize specifications and write delay allowances into leases and loans.
Sources
ColoradoBiz (Reuters, Kavya Balaraman). “US Power Companies Face Transformer Waits as Data Center Demand Grows.” July 9, 2026. https://coloradobiz.com/us-power-companies-transformer-waits-data-center-demand/
Dell’Oro Group via PR Newswire. “Data Center High-Density Power Market to Top $42 Billion by 2030 as AI Racks Move to 800 Vdc.” Nov. 17, 2026. https://www.prnewswire.com/news-releases/data-center-high-density-power-market-to-top-42-billion-by-2030-as-ai-racks-move-to-800-vdc-according-to-delloro-group-302938630.html
electrive. “Alpitronic Builds DC Fast Charger Factory in South Carolina, USA.” Nov. 19, 2026. https://electrive.com/2026/11/19/alpitronic-builds-dc-fast-charger-factory-in-south-carolina-usa
Federal Energy Regulatory Commission. “2026-2027 Winter Energy Market and Electric Reliability Assessment.” Nov. 19, 2026. https://www.ferc.gov/sites/default/files/2026-11/27_Winter%20Energy%20Market%20and%20Electric%20Reliability%20Assessment_1118_1930.pdf
Fortune. “JPMorgan Pegs the U.S. Grid Fix at $1 Trillion. A New Study Says a Transformer Shortage Could Stall It.” Nov. 20, 2026. https://fortune.com/2026/11/20/transformer-shortage-power-grid-johns-hopkins-study/
Johns Hopkins University via EurekAlert! “Transformer Shortages Loom for Strained US Power Grid.” Nov. 17, 2026. https://www.eurekalert.org/news-releases/1151533
Utility Dive. “Fuel Constraints Could Challenge Grid This Winter, Despite Resource Improvements: NERC.” Nov. 19, 2026. https://www.utilitydive.com/news/el-nino-challenge-grid-operators-winter-nerc/875156