Regulators are deciding whether data centers and other loads of 50 MW or more pay the full cost of the power plants and grid upgrades they require, or whether part of that cost spreads to every customer. PJM's market monitor says spreading it has already cost $29.4 billion. The rules being filed at FERC now will set how fast large tenants can connect and how much commercial electric bills rise.
Key Takeaways
PJM’s independent market monitor says data center load has added $29.4 billion to capacity costs for all customers so far, with $5 billion to $10 billion more possible from the December auction.
Wholesale power in PJM cost $111.61 per MWh from January through September, 9.8% more than it would have without data center load’s effect on capacity prices.
Five of six regional grid operators were due November 16 to tell the Federal Energy Regulatory Commission (FERC) how large loads should connect and who pays; the Southwest Power Pool files around November 20.
ISO New England proposes firm, interim and non-firm service, with non-firm users cutting back when local prices reach $250 per MWh, about 1% of hours.
The Senate permitting bill that cleared a 73-25 procedural vote would require new facilities of 20 MW or more to pay the full cost of the grid upgrades they need.
A $29.4 Billion Bill
$29.4 billion. That is what PJM’s independent market monitor, Monitoring Analytics, says data center load has added to capacity market costs for every customer in the 13-state PJM region. Its third-quarter report calls it “an irreversible increase of $29.4 billion in capacity market costs for all customers to date, with more costs to come.”
The effect shows up in the price of power. Wholesale electricity in PJM cost $111.61 per MWh from January through September. Without data center load’s effect on the capacity prices for the last two delivery years, the monitor estimates it would have cost $101.66, a difference of $9.95 per MWh, or 9.8%. That figure leaves out any effect on energy or transmission costs. The monitor estimates the capacity auction scheduled for December, covering 2029 to 2030, could add $5 billion to $10 billion more.
Other researchers see the same pattern nationally. A Federal Reserve Bank of Dallas working paper estimates data center demand raised U.S. wholesale electricity prices 6.9% by 2025, and 15% in Northern Virginia. Capacity charges flow into commercial electric bills through supply contracts and utility rates, so owners across the PJM region are paying part of the cost of serving loads they do not host.
The Monitor’s Fix: Make Large Loads Bring Their Own Power
The monitor’s recommendations would move that cost to the loads that cause it. It asks PJM to postpone the December auction until forecast data center load can be removed, to run a separate backstop auction for data centers that lack a supply contract, and to move data centers to bilateral contracts with generators, including arrangements to bring their own new generation. It proposes a queue so large data centers connect only when there is capacity to serve them, and a faster interconnection path for those that bring their own supply. “Data center loads should pay their own costs and cover their own risks,” the report says.
PJM has already tried one version of that approach. In October, FERC rejected PJM’s proposed interim service that would have let large loads connect during capacity shortfalls if they accepted curtailment, along with its bring-your-own-capacity provisions, finding that the design reached too far into retail service, according to an analysis by AIxEnergy. FERC accepted PJM’s definition of a large load and its registry. The question returned to FERC on the November 16 filing deadline, in a broader proceeding.
Six Grid Operators, One Question
In June, FERC ordered all six regional grid operators to justify or reform their rules for connecting large loads. The orders covered study timelines, protections against shifting costs to other customers, co-location with power plants, flexible loads that can limit their use of the grid and loads located near existing generation. FERC also asked each operator to explain how it will ensure enough generation for new and existing load. PJM, the Midcontinent Independent System Operator (MISO), the California Independent System Operator (CAISO), ISO New England and the New York Independent System Operator (NYISO) had until November 16 to respond. The Southwest Power Pool (SPP), which already has a large-load framework in its tariff, files around November 20, after this issue publishes.
ISO New England filed first, on November 13. Its proposal offers three kinds of service. Firm service carries the same priority as other customers but requires new capacity to match the load and the transmission upgrades to deliver it. Interim service lets a customer connect while it works toward firm service. Non-firm service is a permanent option for flexible loads that need fewer upgrades. Interim and non-firm customers would cut consumption or run onsite generation when local prices reach $250 per MWh, which ISO New England says happens in about 1% of hours. The grid operator said the goal is to “avoid shifting costs to consumers.” The process would take effect June 1, 2027.
The details vary by region. Most operators use a 50 MW threshold for large loads, while MISO applies 200 MW for its joint load and generation study. Study clocks run from 60 to 120 days. ISO New England stakeholder materials cite a $50,000 application fee, a $150,000 study deposit and a $10,000 per MW readiness deposit, according to AIxEnergy’s review of the filings.
Washington Adds a 20 MW Line
Congress is writing a similar rule. The Bipartisan American Affordability and Jobs Act, S. 5653, which the Senate advanced 73-25 on November 9, would require new facilities of 20 MW or more to pay the full cost of the grid upgrades built to serve them. Final Senate passage and House action are still ahead.
Taken together, the federal bill, FERC’s proceeding and the market monitor’s recommendations point the same way: the cost of new large loads moves toward the loads themselves, through deposits, minimum payments, curtailment obligations or self-supplied power.
The Utilities Write Their Own Terms
Utilities are not waiting for the regional rules. On October 9, the same day it rejected PJM’s interim service, FERC accepted changes by Duke Energy Carolinas that require large loads of at least 100 MW to sign a 15-year minimum revenue commitment based on 75% of their scheduled megawatts, according to AIxEnergy. In Virginia, Dominion Energy’s new GS-5 rate class for very large customers takes effect January 1, 2027. PJM’s separate reliability backstop procurement was accepted and suspended, with a February 28, 2027, effective date.
Minimum payments address only part of the exposure. AIxEnergy’s analysis identifies three costs other customers can carry: stranded investment if promised demand never arrives, shared network costs even when the load shows up as planned, and regional capacity and energy price effects. A minimum bill protects against the first. The market monitor’s $29.4 billion figure belongs to the third, which no contract between one utility and one customer can fully cover.
The debate inside FERC reflects the same tension. Commissioner David Rosner questioned curtailing large loads before calling on voluntary demand response, and Commissioner Judy Chang dissented on how financial security and network upgrade costs are treated in shared rates, according to AIxEnergy’s account of the October orders. Those positions will shape how the commission reads the November 16 filings.
What It Means for Owners and Developers
Implication: Data center tenancy gets more expensive to underwrite. Deposits, financial security and curtailment terms will appear in power agreements for any tenant above 50 MW, and in some regions above 20 MW once the federal bill applies.
Implication: Commercial bills may stop absorbing as much of the cost. If regulators move capacity costs to new large loads, the pressure on other customers eases over time, though the $29.4 billion already incurred stays in rates.
Opportunity: Flexible load gets a faster lane. Non-firm and interim service reward loads that can cut back during the roughly 1% of hours when prices spike. Buildings and campuses with batteries, onsite generation or controllable processes fit that profile.
Opportunity: Sites with existing capacity gain value. Land near available capacity, or with room for onsite generation, becomes more marketable to large tenants as connection rules tighten.
Risk: Timelines stay uncertain. FERC has not ruled on the new filings, SPP has yet to file, the December auction may proceed as scheduled, and the federal bill has not passed. Leases signed now should allow for rule changes - the rules being filed now will determine how quickly large tenants can connect and how much commercial electric bills rise.
Frequently Asked Questions
How much have data centers added to PJM power costs?
PJM’s independent market monitor says data center load has added $29.4 billion to capacity market costs to date and raised wholesale costs 9.8% from January through September 2026.
What is a large load under the new rules?
Most regional grid operators use a 50 MW threshold. MISO uses 200 MW for its joint study product, and the Senate bill uses 20 MW for its cost provision.
What is non-firm service?
Service for flexible loads that agree to cut consumption or run onsite generation when local prices spike. ISO New England proposes a $250 per MWh trigger, about 1% of hours.
When will the new rules take effect?
ISO New England proposes June 1, 2027. FERC must still review all filings, and SPP files around November 20. ChargedUp! will continue to follow the story and report on further developments.
Sources
AIxEnergy (Brandon N. Owens). “After FERC Said No: Who Now Decides How AI Load Connects, and Who Pays.” Oct. 21, 2026. https://www.aixenergy.io/after-ferc-said-no-who-now-decides-how-ai-load-connects-and-who-pays/
AIxEnergy (Brandon N. Owens). “Six Answers on November 16: A Developer’s Scorecard for FERC’s Large-Load Show-Cause Filings.” Nov. 13, 2026. https://www.aixenergy.io/ferc-large-load-show-cause-scorecard/
Congress.gov. “S.5653, Bipartisan American Affordability and Jobs Act of 2026: Text.” 2026. https://www.congress.gov/bill/119th-congress/senate-bill/5653/text
Construction Review Online. “U.S. Grid Operators Rework Power Connection Rules as Data Center Demand Surges.” Nov. 16, 2026. https://constructionreviewonline.com/u-s-grid-operators-rework-power-connection-rules-as-data-center-demand-surges/
Federal Reserve Bank of Dallas. “Processing Power: Data Centers and Wholesale Electricity Prices (Working Paper 2606).” Revised Oct. 2026. https://www.dallasfed.org/research/papers/2026/wp2606
FERC. “Cost Transparency and Customer Protection Initiatives in FERC’s June 2026 Show Cause Orders for Large Load Interconnections.” Nov. 16, 2026. https://www.ferc.gov/cost-transparency-customer-protection
Foley & Lardner. “FERC Issues Six Tailored Show Cause Orders to Accelerate Large Load Interconnection.” June 2026. https://www.foley.com/insights/publications/2026/06/ferc-issues-six-tailored-show-cause-orders-to-accelerate-large-load-interconnection/
ISO New England (ISO Newswire). “ISO-NE Files Proposal With FERC to Address Large Loads.” Nov. 13, 2026. https://isonewswire.com/2026/11/13/iso-ne-files-proposal-with-ferc-to-address-large-loads/
McGuireWoods. “FERC Issues Section 206 Show Cause Orders Directing All Six RTOs/ISOs to Justify or Reform Large Load Integration Rules.” June 2026. https://www.mcguirewoods.com/client-resources/alerts/2026/6/ferc-issues-section-206-show-cause-orders-directing-all-six-rtos-isos-to-justify-or-reform-large-load-integration-rules/
Monitoring Analytics (Independent Market Monitor for PJM). “2026 Quarterly State of the Market Report for PJM: January Through September, Section 1.” Nov. 12, 2026. https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2026/2026q3-som-pjm-sec1.pdf
RTO Insider. “Senate Permitting Reform Bill Comfortably Clears Cloture Vote.” Nov. 9, 2026. https://www.rtoinsider.com/151021-senate-permitting-reform-bill-comfortably-clears-cloture-vote/