Local governments are pausing data center approvals while they write zoning rules, and the November elections gave those pauses political momentum. The world's largest data center market, Loudoun County, Virginia, joined the trend on November 17. Rystad Energy expects stricter grid terms to change how data centers grow more than how fast, which shifts value toward sites with zoning, power and approvals already in hand.
Key Takeaways
Loudoun County, Virginia, paused board decisions on legislative data center and substation applications for up to 12 months, retroactive to September 15.
McHenry County, Illinois, and Rutherford County, Tennessee, adopted one-year data center moratoriums in November.
Nearly all of the 46 municipal ballot measures on data centers tracked by Bloomberg produced restrictions, moratoriums or bans, Utility Dive reported.
Orennia puts 191 GW of planned data center capacity at new risk; Rystad Energy expects 121 GW to be added from 2027 to 2030; Modo Energy counts 165 GW in states whose incoming governors back immediate moratoriums.
Most at-risk capacity is still proposed, so land deals tied to early-stage projects carry the most exposure.
The World’s Largest Market Takes a Timeout
58 million square feet. That is the data center space built or under construction in Loudoun County, across about 245 buildings, with another 55 million square feet approved or under review, according to the county. On November 17, its Board of Supervisors voted 7-1-1 to pause hearings and final votes on legislative data center and substation applications for up to 12 months while staff finishes the second phase of new data center standards, expected in July 2027. Thirty-three legislative applications are pending, and at least nine are expected to reach their deadline for final board action before the new standards are finished.
“Loudoun County residents have been begging us to get our arms around unchecked data center sprawl,” said Supervisor Juli E. Briskman. The county attorney had advised that an indefinite moratorium would be illegal, so the board used Virginia law that requires action on legislative applications within a reasonable time, not exceeding 12 months. The clock runs separately for each application from its Planning Commission review, and staff and the commission keep processing filings.
The pause has limits. Grid reliability substations and certain Route 28 District applications are exempt, and projects that proceed through administrative permits fall outside it. Applications filed before February 12, 2025, may still qualify for prior zoning rules. Potomac Law Group warns that the county’s legal position “does not eliminate litigation risk” and that “filing an application alone does not necessarily establish vested rights.”
The Suburbs Follow
The same evening, the McHenry County Board in Illinois approved a 12-month moratorium on new data center applications in unincorporated areas, a 17-1 vote according to the Northwest Herald. The county will not accept, review or approve any zoning change or permit, including a building permit, that would allow a data center. Its zoning code does not define data centers or permit them in any district, and the planning director said no developer has applied. “We need time to catch up,” said Vice Chair Joseph Gottemoller. Neighboring Lake County adopted an eight-month moratorium in September. Board member Mike Shorten said the county “can only do so much” and that state and federal lawmakers need to act.
Rutherford County, Tennessee, southeast of Nashville, adopted a 12-month pause unanimously on November 12, effective immediately, because the county lacks rules for these facilities, its planning director said. The pattern extends to the ballot box: nearly all of the 46 municipal measures on data centers that Bloomberg tracked produced restrictions, moratoriums or bans, Utility Dive reported.
What the Numbers Say
Three analyses published this month estimate how much capacity the shift puts in play. Energy analytics firm Orennia estimates that 191 GW of planned capacity faces new risk, concentrated in Texas, Ohio and Georgia. AEP Ohio’s large-load pipeline has already fallen from more than 30 GW to about 13 GW since regulators approved a tariff requiring data centers above 25 MW to pay for at least 85% of requested capacity for up to 12 years.
Rystad Energy finds that incoming Democratic governors will lead states holding 77% of the 300 GW announced for 2027 to 2030, including Texas, Virginia, Pennsylvania, Ohio and Georgia. Its risked forecast adds 121 GW over that period. If pauses in Texas run another year, more than 10 GW slips, and installed capacity at the end of 2029 reaches about 170 GW, compared with 177 GW.
Modo Energy counts 165 GW, or 26% of the 633 GW it tracks, in states whose incoming governor backs an immediate moratorium. Of the 242 GW not yet operating in those states, 41 GW is under construction and 201 GW is proposed. The exposure sits mostly in projects that exist on paper.
Grid Terms Replace Open Doors
Rystad expects the midterms to change the terms of growth more than its pace. Virginia will require 14-year commitments and collateral of up to $1.5 million per megavolt-ampere for contracts signed from January, and similar rules cover states with more than half of planned capacity. About half of Texas’s planned capacity would generate its own power, but Rystad says a new pause would likely catch most of those projects because air permits take longer than the two-month window.
The federal permitting bill points the same way. It would shield other customers from the added cost of serving new data centers and create a DOE program to give local governments independent data on power, water and tax effects. Utilities, legislators and county boards now ask the same question before approving a large load: who carries the cost if the project shrinks or leaves?
What It Means for Owners, Developers and Planners
Implication: Entitled land gains value. Sites with by-right data center zoning, approved applications or vested rights become the clearest near-term path in markets that pause legislative approvals.
Risk: Early-stage land contracts carry timing risk. Purchase agreements tied to rezonings, special exceptions or utility commitments should extend contingency periods and address pause scenarios.
Implication: Collateral moves into the capital stack. Commitments of 12 to 14 years and per-megawatt collateral raise the equity and credit required of data center tenants and developers.
Opportunity: Planners can write rules on their own schedule. Counties without data center definitions can use pause periods to set setbacks, noise, water and power standards, and to ask for the DOE review the Senate bill would create.
Implication: Onsite power gains appeal. Higher grid costs and curtailment rules strengthen the case for campuses that bring their own generation and storage.
Frequently Asked Questions
Is Loudoun County banning data centers?
No ban applies. The board paused hearings and votes on legislative applications for up to 12 months per application while it writes new standards. Staff review continues, and some substations and administrative permits are outside the pause.
How much data center capacity is at risk after the midterms?
Estimates range from Orennia’s 191 GW at new risk to Modo Energy’s 165 GW in states whose incoming governors back immediate moratoriums. Rystad expects 121 GW to be added from 2027 to 2030.
Which counties adopted moratoriums this month?
McHenry County, Illinois, and Rutherford County, Tennessee, each adopted 12-month moratoriums in November.
What should landowners do?
Confirm whether a project needs legislative approval, check decision deadlines and vested-rights status and build pause scenarios into contract timelines.
Related Reading on ChargedUp!
Sources
Bipartisan Policy Center. “Explaining the Senate Permitting Bill, the Bipartisan American Affordability and Jobs Act.” Nov. 2026. https://bipartisanpolicy.org/explainer/explaining-the-senate-permitting-bill-the-bipartisan-american-affordability-and-jobs-act/
Lake and McHenry County Scanner. “McHenry County Board Approves 12-Month Ban on New Data Centers in Unincorporated Areas.” Nov. 20, 2026. https://www.lakemchenryscanner.com/2026/11/20/protect-people-first-mchenry-county-board-approves-12-month-ban-on-new-data-centers-in-unincorporated-areas/
Loudoun County Board of Supervisors (Office of Supervisor Briskman). “Loudoun Board Formally Adopts Data Center Pause.” Nov. 18, 2026. https://www.loudoun.gov/DocumentCenter/View/223074/Release---Loudoun-Board-Formally-Adopts-Data-Center-Pause
Loudoun County. “Loudoun Board Pauses Legislative Data Center and Substation Applications.” Nov. 18, 2026. https://www.loudoun.gov/m/NewsFlash/Home/Detail/10993
Modo Energy. “U.S. Midterm Election Could Disrupt 25% of Data Center Capacity.” Nov. 2026. https://modoenergy.com/research/us-data-center-moratorium-midterms
Northwest Herald (Shaw Local). “McHenry County Board Approves Year-Long Data Center Moratorium.” Nov. 22, 2026. https://www.shawlocal.com/northwest-herald/2026/11/22/mchenry-county-board-approves-year-long-data-center-moratorium/
Potomac Law Group. “Loudoun County, VA Pauses Data Center Approvals: Legal and Business Implications.” Nov. 2026. https://www.potomaclaw.com/news-PLG-US-Data-Centers-Loudoun-County-VA-Pauses-Data-Center-Approvals-Legal-and-Business-Implications
Rystad Energy (Minh Khoi Le and Victoria Fethke). “Blue Wave Likely to Change Terms of US Data Center Growth, but Not the Pace.” Nov. 2026. https://www.rystadenergy.com/insights/blue-wave-likely-to-change-terms-of-us-data-center-growth-but-not-the-pace
Utility Dive (Marlene Wilden). “Data Center Slowdown Would Raise Risks for Utility Investments.” Nov. 17, 2026. https://www.utilitydive.com/news/data-center-slowdown-raises-risks-for-utility-investments/874924/
WKRN. “Rutherford County Approves 12-Month Data Center Moratorium.” Nov. 23, 2026. https://www.wkrn.com/news/local-news/rutherford-county-approves-12-month-data-center-moratorium/