The Senate bill would make data centers pay the added grid costs they create, starting with a FERC pricing rule due within 90 days of enactment. For owners of offices, apartments, retail centers and industrial parks, that means less of the next wave of grid spending lands on their utility bills. The bill also speeds transmission approvals and shortens court challenges, which changes how quickly power reaches new sites.
Key Takeaways
The Senate passed the Bipartisan American Affordability and Jobs Act (BAAJA) 62-33 on November 19 and sent it to the House.
The bill directs the Federal Energy Regulatory Commission (FERC) to rewrite its pricing policy within 90 days so other customers are shielded from the added cost of serving new data centers of any size.
Data centers would post financial guarantees before utilities build for them, keep paying if they leave early and pay less if they accept interruptible service.
FERC would gain backstop authority to site transmission lines of 230 kV or more once a state has had a year to act.
Environmental lawsuits would have to be filed within 150 days, and courts would leave permits in place while agencies fix errors.
62-33 was the final tally on Thursday night, November 19, when the Senate passed the Bipartisan American Affordability and Jobs Act, a nearly 500-page rewrite of federal permitting law that rode on a House tax measure, H.R. 2347, as its vehicle. Support narrowed as senators read the details. The first procedural vote on November 9 passed 73-25, a November 16 vote passed 70-27 and the final cloture vote on November 18 passed 65-31, according to the Center for Western Priorities, which opposed the bill.
Senators Shelley Moore Capito (R-W.Va.), Martin Heinrich (D-N.M.), Mike Lee (R-Utah) and Sheldon Whitehouse (D-R.I.) introduced the bill in late September. Supporters came from both parties. Sen. Chris Coons (D-Del.) said it will “ensure data centers pay more than their fair share in the communities they impact.” The office of Sen. Katie Britt (R-Ala.) said the bill “sets firm deadlines on process reviews and puts an end to frivolous lawfare.” The bill now goes to the House.
Who Pays for the Next Data Center
Section 2107 is the provision property owners should read first. According to the Bipartisan Policy Center’s explainer of the Senate-passed text, FERC would have 90 days to revise its pricing policy so that new and existing data centers pay their share of the existing transmission system plus an estimate of the added cost they cause. “For new data centers of any size, other customers would not be charged for the added costs of serving them,” the explainer says.
The section also addresses stranded assets. Data centers would provide financial guarantees before utilities build to serve them and would keep paying if they leave early. Facilities that accept flexible or interruptible service would pay less. States keep wide latitude: they could charge data centers above cost and apply the extra revenue to other customers’ bills, limit which facilities connect, require them to bring their own generation or cap how much power they draw.
Indiana shows the kind of split the bill targets. When state regulators approved AES Indiana’s plan to serve a 390 MW Google data center in October, Google agreed to pay about $32 million upfront for direct connection, while $73.8 million in network upgrades entered the utility’s transmission rate base for recovery from all customers, Utility Dive reported. AES Indiana says Google’s revenue more than offsets that share. A federal pricing rule could set a national standard for how such upgrades are charged.
Faster Lines and Shorter Lawsuits
The bill’s transmission sections matter as much as its data center rules, because new lines decide where power can reach. BAAJA would codify FERC Order 1920, requiring regional and interregional planning on common assumptions, and would bar charging customers who receive no benefit, or only trivial benefits, from a project. Grid operators would plan generation and transmission together over 20 years and publish connection points with upfront fees.
Once a state has had a year to act on a line of 230 kV or more, or any line selected in an approved regional plan, FERC would be required to issue a permit if it finds the project serves the public interest. The backstop excludes the Electric Reliability Council of Texas (ERCOT).
Court timelines shrink. Challenges under the National Environmental Policy Act (NEPA) would have to be filed within 150 days, down from six years, and only by parties that commented and can show direct harm. Courts would send flawed reviews back to agencies while the permit stays in effect. Agencies would issue a record of decision within 45 days of a final environmental impact statement. The Center for Western Priorities says these changes weaken bedrock environmental laws.
A Help Desk for Local Governments
Section 2117 gives planners a new resource. Within 180 days, the U.S. Department of Energy (DOE) would create a Data Center Community Assistance Program to give state, local and tribal governments objective information on electricity demand, grid upgrade costs, water use, backup generation, jobs and tax effects, plus a plain-language guide for officials without technical staff.
At a government’s request, DOE could ask a developer to share data and test its assumptions. The department must stay neutral and cannot recommend approval, and the section authorizes no specific funding. For counties weighing their first data center application, it offers a second opinion on the numbers a developer brings to the hearing.
The House Sets the Timing
Enactment depends on the House. Democratic lawmakers there were working on changes before the Senate vote, and some wanted to wait until their party takes control of Congress in January, Reuters reported on November 14. Any change to the Senate text would send it back for another vote.
For property owners, the policy direction is set even if the calendar is not. The Senate bill, FERC’s large-load proceeding and new state utility rules all move the cost of new large loads toward the loads themselves.
What It Means for Owners and Developers
Implication: Commercial bills absorb less of future data center growth. If the pricing rule takes effect, network upgrade costs caused by new data centers shift to those customers. Costs already in rates stay there.
Implication: Data center tenancy carries more paperwork. Financial guarantees and early-exit payments will appear in power agreements for data center tenants, which affects lease structure and credit review for powered-shell developers.
Opportunity: Flexible load earns a discount. Campuses and industrial sites with batteries, onsite generation or controllable processes can qualify for lower-cost interruptible service.
Opportunity: Transmission reaches stalled sites sooner. Backstop siting and shorter litigation windows shorten the timeline for lines that serve growth corridors.
Risk: The House may rewrite it. Owners should model both outcomes in 2027 budgets and avoid lease terms that assume enactment.
Frequently Asked Questions
What did the Senate pass?
The Bipartisan American Affordability and Jobs Act, a permitting and transmission bill that passed 62-33 on November 19, 2026, and now goes to the House.
How does the bill treat data center costs?
It directs FERC to revise its pricing policy within 90 days so that other customers are shielded from the added cost of serving new data centers of any size.
Does the bill override state utility regulators?
States keep authority to charge data centers above cost, limit connections, require onsite generation or cap power draw.
What changes for transmission?
FERC gains backstop siting authority for lines of 230 kV or more after a state has had a year to act, and NEPA lawsuits must be filed within 150 days.
Related Reading on ChargedUp!
Sources
Bipartisan Policy Center. “Explaining the Senate Permitting Bill, the Bipartisan American Affordability and Jobs Act.” Nov. 2026. https://bipartisanpolicy.org/explainer/explaining-the-senate-permitting-bill-the-bipartisan-american-affordability-and-jobs-act/
Center for Western Priorities. “Senate Passes BAAJA, Which Weakens Bedrock Environmental Laws.” Nov. 2026. https://westernpriorities.org/2026/11/senate-passes-baaja-which-weakens-bedrock-environmental-laws-and-locks-in-trumps-future-attacks-on-public-lands/
GV Wire (Reuters). “As Democrats Seek Changes to Bill on Energy Permits, Divisions Emerge.” Nov. 14, 2026. https://gvwire.com/?p=278088
Office of Sen. Chris Coons. “Senator Coons Statement on Final Passage of Permitting Reform Bill.” Nov. 19, 2026. https://www.coons.senate.gov/news/press-releases/senator-coons-statement-on-final-passage-of-permitting-reform-bill/
Office of Sen. Katie Britt. “U.S. Senator Katie Britt Votes to Pass Bipartisan American Affordability and Jobs Act.” Nov. 19, 2026. https://www.britt.senate.gov/news/press-releases/u-s-senator-katie-britt-votes-to-pass-bipartisan-american-affordability-and-jobs-act/
The Wildlife Society. “Senate Passes the Bipartisan American Affordability and Jobs Act.” Nov. 20, 2026. https://wildlife.org/senate-passes-the-bipartisan-american-affordability-and-jobs-act
Utility Dive (Charles Paullin). “Are Data Centers Really Paying Their Share? AES Indiana’s Google Deal Highlights a Thorny Question.” Nov. 10, 2026. https://www.utilitydive.com/news/are-data-centers-really-paying-aes-indianas-google-deal-highlights-a-thor/873040/